Timing is Everything: Defining Project Review Periods Through Monte Carlo Simulation and Machine Learning

Vol 57, 2025 - 324772
Poster
Favorite this paper
How to cite this paper?
Abstract

Project monitoring practices have significantly evolved over the past decades, progressing from traditional methodologies such as Earned Value Management (EVM) to the incorporation of control charts and advanced Machine Learning (ML) techniques. Yet, one fundamental question remains unanswered: When should a project be monitored?

This work proposes an integrated methodology to define optimal review periods based on predefined criteria, enabling early detection of potential delays. Specifically, we combine Earned Duration Management (EDM) with Monte Carlo simulation to generate a comprehensive dataset, and apply ML models enhanced with the Boruta feature selection algorithm to identify eight key monitoring points capable of predicting project delays with minimal performance loss. To address the highly correlated nature of the data, we employ experimental design to evaluate the effects of different preprocessing techniques and ML models on predictive performance.

The methodology was validated on a real-world project, where the number of monitoring points was substantially reduced — from 25 to 8 — with less than 0.5% performance loss, demonstrating the effectiveness of the proposed approach in improving project monitoring efficiency.

Share your ideas or questions with the authors!

Did you know that the greatest stimulus in scientific and cultural development is curiosity? Leave your questions or suggestions to the author!

Sign in to interact

Have a question or suggestion? Share your feedback with the authors!

Institutions
  • 1 Universidade de São Paulo
Track
  • 9. EST&MP – Statistics and Probabilistic Models
Keywords
statistical project monitoring
machine learning
monte carlo simulation