Project monitoring practices have significantly evolved over the past decades, progressing from traditional methodologies such as Earned Value Management (EVM) to the incorporation of control charts and advanced Machine Learning (ML) techniques. Yet, one fundamental question remains unanswered: When should a project be monitored?
This work proposes an integrated methodology to define optimal review periods based on predefined criteria, enabling early detection of potential delays. Specifically, we combine Earned Duration Management (EDM) with Monte Carlo simulation to generate a comprehensive dataset, and apply ML models enhanced with the Boruta feature selection algorithm to identify eight key monitoring points capable of predicting project delays with minimal performance loss. To address the highly correlated nature of the data, we employ experimental design to evaluate the effects of different preprocessing techniques and ML models on predictive performance.
The methodology was validated on a real-world project, where the number of monitoring points was substantially reduced — from 25 to 8 — with less than 0.5% performance loss, demonstrating the effectiveness of the proposed approach in improving project monitoring efficiency.
Com ~200 mil publicações revisadas por pesquisadores do mundo todo, o Galoá impulsiona cientistas na descoberta de pesquisas de ponta por meio de nossa plataforma indexada.
Confira nossos produtos e como podemos ajudá-lo a dar mais alcance para sua pesquisa:
Esse proceedings é identificado por um DOI , para usar em citações ou referências bibliográficas. Atenção: este não é um DOI para o jornal e, como tal, não pode ser usado em Lattes para identificar um trabalho específico.
Verifique o link "Como citar" na página do trabalho, para ver como citar corretamente o artigo