Timing is Everything: Defining Project Review Periods Through Monte Carlo Simulation and Machine Learning

Vol 57, 2025 - 324772
Pôster
Favoritar este trabalho
Como citar esse trabalho?
Resumo

Project monitoring practices have significantly evolved over the past decades, progressing from traditional methodologies such as Earned Value Management (EVM) to the incorporation of control charts and advanced Machine Learning (ML) techniques. Yet, one fundamental question remains unanswered: When should a project be monitored?

This work proposes an integrated methodology to define optimal review periods based on predefined criteria, enabling early detection of potential delays. Specifically, we combine Earned Duration Management (EDM) with Monte Carlo simulation to generate a comprehensive dataset, and apply ML models enhanced with the Boruta feature selection algorithm to identify eight key monitoring points capable of predicting project delays with minimal performance loss. To address the highly correlated nature of the data, we employ experimental design to evaluate the effects of different preprocessing techniques and ML models on predictive performance.

The methodology was validated on a real-world project, where the number of monitoring points was substantially reduced — from 25 to 8 — with less than 0.5% performance loss, demonstrating the effectiveness of the proposed approach in improving project monitoring efficiency.

Compartilhe suas ideias ou dúvidas com os autores!

Sabia que o maior estímulo no desenvolvimento científico e cultural é a curiosidade? Deixe seus questionamentos ou sugestões para o autor!

Faça login para interagir

Tem uma dúvida ou sugestão? Compartilhe seu feedback com os autores!

Instituições
  • 1 Universidade de São Paulo
Eixo Temático
  • 9. EST&AM – PO Analytics em Estatística e Aprendizado de Máquina
Palavras-chave
statistical project monitoring
machine learning
monte carlo simulation