This study introduces the methodology of the commercial optimization software OptMain, developed by PSR Energy Consulting and Analytics to address power system maintenance scheduling. The problem is built as a MIP (Mixed Integer Programming) multi-objective optimization model, where the users can use a graphical interface in an integrated environment for analyzing and calculating optimal operating policies.
Defining operating policies for energy systems is crucial to align generation with demand. Simultaneously, maintaining an available capacity, called reserve margin, is vital to cover contingencies, fluctuations, and failures. Balancing the reserve margin with essential plant maintenance is a planner's challenge, ensuring functionality and operational efficiency. To mitigate system risk, maintenance must be strategically centralized, considering energy demand and generation seasonality.
This model aims to be applied to the scheduling of real power systems, targeting an optimal reserve policy while respecting technical operational constraints. It has been tested on cases with up to 800 maintenances scheduled over two years, managing to allocate approximately half of them on its preferred date. That problem yields an order of 800000 variables and 250000 constraints, most of which are soft, that is, can be violated under a priority arrangement to accommodate infeasibilities of real-life inconsistent data. While not damaging the optimal reserve margin, the model also considers a preference parameter defined by the system planner, so that, for instance, a maintenance requested in advance may have high priority over one requested later.
The input data were defined considering the set of constraints that the user can configure. The main one is the set of maintenances that must be carried out uninterruptedly. These are represented individually as a maintenance request for a given plant unit, with well-defined duration, and minimum, maximum, and preferred dates. The minimum date corresponds to the minimum day on which maintenance must begin, the maximum to the maximum day on which it must end, and the preferred date is the exact date inside that window when the plant manager would like the maintenance to begin. Other constraint options include groups of generators that must not go into maintenance simultaneously, minimum reserve at each stage, and forbidden maintenance periods for each plant.
The problem is modeled as a lexicography optimization problem. It has two objective functions, a main one, and a second one that breaks ties between equivalent solutions regarding the main one. The model's main objective is to maximize the minimum daily reserve margin along the study horizon. Once that optimal reserve value is determined, another optimization is executed with the optimal reserve solutions as the feasible space maximizing the maintenances on its preferred dates, weighted by its priority.
Com ~200 mil publicações revisadas por pesquisadores do mundo todo, o Galoá impulsiona cientistas na descoberta de pesquisas de ponta por meio de nossa plataforma indexada.
Confira nossos produtos e como podemos ajudá-lo a dar mais alcance para sua pesquisa:
Esse proceedings é identificado por um DOI , para usar em citações ou referências bibliográficas. Atenção: este não é um DOI para o jornal e, como tal, não pode ser usado em Lattes para identificar um trabalho específico.
Verifique o link "Como citar" na página do trabalho, para ver como citar corretamente o artigo