Optimization of production Sequencing with order-dependent Changeover time via application of the Traveling Salesman Formulation

Vol 57, 2025 - 340249
Poster
Favorite this paper
How to cite this paper?
Abstract

The present work addresses the production sequencing with order-dependent changeover time in a tempering production line. The bibliographic analyses demonstrated the possibility of using the traveling salesman formulation for this theme. A Python model was developed with the Pyomo tool and the Cplex solver. The solutions obtained were analyzed in detail for the case of 4 and 20 materials, which were validated according to the physical reality of the process. A study of calculation times and a comparison between solvers are made. In the end, it was verified the possibility of incorporating an improvement in energy consumption into the model, based on the evaluation of temperature variations. This improvement also proved to be valid. The final tool built is then a viable alternative to propose good production sequences in terms of total exchange time and energy consumption. The great contribution is the elaboration of a viable and coherent tool to support the production programming of a Heat Treatment line.

Share your ideas or questions with the authors!

Did you know that the greatest stimulus in scientific and cultural development is curiosity? Leave your questions or suggestions to the author!

Sign in to interact

Have a question or suggestion? Share your feedback with the authors!

Institutions
  • 1 Universidade Federal do Rio Grande do Sul
  • 2 Universidade Federal de Minas Gerais
Track
  • POI – OR in Industry
Keywords
Production Sequencing
Setup Time Dependent on Sequence
Traveling Salesman Problem