In 2012, Ecorodovias Group concluded the acquisition of 100% of Tecondi shares. Tecondi is a Deep-Sea Terminal at Santos Port which main focuses are container and general cargo operations.

A few months after the acquisition, mother company decided to implement an investment plan at Terminal where the main objective was to achieve the maximum throughput capacity in the most cost effective, productive and customer responsive way.

For a balanced design of terminal layout, handling capacity, storage capacity and operating costs are considered and these three aspects will lead to a terminal configuration that can handle the peak loads, both handling and storage wise against the lowest possible costs.

Before the acquisition, Terminal main equipment were Mobile Harbor Cranes, Reach stackers, conventional trucks linking quay to yards and an old fashion TOS System.

Several studies and simulations were done to define the best design for the terminal. The final decision requested a total investment of USD 50MM to improve its equipment portfolio and the TOS System. In one hand, the level of service, annual capacity, productivity and safety were improved and, on the other hand, operational costs and emissions were reduced.

Considering the importance and impact of such investment at Terminal, a multidisciplinary team was created to prepare it to receive and operate the equipment properly. All the activities followed the support of MS Project software, handled by the PMO. Investment plan breakdown, physical and financial schedule were followed by the same team. The PMO was in charge to handle the project, in line with the physical and financial schedules that were agreed with Board of Directors.

Investment plan was implemented successfully, in line with the schedule, budget and technical aspects. Currently, investment plan is concluded and the equipment is already operating at terminal.