HEURISTIC FOR THE M-MACHINE NO-WAIT FLOW SHOP SCHEDULING PROBLEM WITH HIERARCHICAL OBJECTIVE

Vol 51, 2019 - 108887
Prêmio de IC
Favorite this paper
How to cite this paper?
Abstract

This paper addresses the m-machine no-wait flow shop scheduling problem. Two hierarchical objective functions are considered: (1) minimizing makespan subject to the constraint that mean completion time is less than or equal to a given value; and (2) minimizing total completion time subject to the constraint that makespan is less than or equal to a given value. For each objective, an Iterated Greedy with Local Search (IGLS) algorithm is proposed. Computational experiments were performed to evaluate the performance of IGLS against other heuristics in the literature. The results show that the IGLS outperform the other methods in both effectiveness and efficiency.

Share your ideas or questions with the authors!

Did you know that the greatest stimulus in scientific and cultural development is curiosity? Leave your questions or suggestions to the author!

Sign in to interact

Have a question or suggestion? Share your feedback with the authors!

Institutions
  • 1 Departamento de Engenharia de Produção / Escola de Engenharia de São Carlos / Universidade de São Paulo
  • 2 Escola de Engenharia de São Carlos / Universidade de São Paulo
Track
  • AD&GP – PO na Administração e Gestão da Produção
Keywords
No-wait flowshop
Makespan
Mean completion time